Projects

Project Status List


Road Paving Projects
     Construction Projects     City Sidewalk Pilot Project     Planning Projects

Road Paving Projects

Rocky Ridge Road – Vestavia Hills portion of Rocky Ridge construction is complete
Columbiana Rd. / Tyler Rd. / Overton Rd. – paving and striping are complete, awaiting completion of miscellaneous punch list items  See Project Limits
Massey Rd. – in design phase, projected to start in 2017
Sicard Hollow Rd. – bid date December 5, 2016, projected start 2017 (Jefferson County project)
Miscellaneous Residential Paving – in progress
Cahaba River Road – multi-jurisdictional agreement approval pending (Jefferson County project lead)
Manor Brook – construction complete June 2016

Residential Paving Program

2016 Three Year Residential Paving Program Map
2016 Three Year Residential Paving Program List
2016 Residential Paving Program I-A – paving work anticipated to begin late Fall

City Sidewalk Pilot Project

Merryvale Road- construction completed
Willoughby Road – see project schedule projected start January 2017
Green Valley Road – surveys conducted Fall 2016

Construction Projects

Patchwork Infrastructure – currently under construction, projected completion end-of-year 2016
US 31 Pedestrian Bridge – ALDOT approval anticipated Spring 2017 see conceptual design  see location map
Liberty Park Pedestrian Tunnel – in design phase, projected bid 2017
Meadowlawn Park – under construction, projected completion 2017
Library ADA Ramp – currently under construction, projected completion 2017
Motor Scout Building – in design phase, projected start 2017
Fleet Operations Building – in design phase, projected start 2017
Public Works Building – in design phase, projected start 2017
Altadena Valley Western Entrance – in design phase, projected start Winter 2017
Sicard Hollow Athletic Complex (SHAC) Phase II – construction to start September 1, 120 day construction period projected
Wald Park Pool Resurfacing – construction complete May 2016
Highway 31 Landscaping – complete June 2016

 

 

Planning Projects

Cahaba Heights Ballfield Renovations – to begin October 2016
Acton Road APPLE Grant (Feasibility Study) – in design phase
Wald Park Master Plan – Phase III in progress July 2016, see update