Altadena Valley Park Trail Extension
Provide pedestrian connectivity to dead end sections of existing cart paths; remove/repair high hazard bridges.
Activity / Status
Finalize design for path extensions and bid project in summer of 2026.
Location
Altadena Valley Park
Managing Organization
City of Vestavia Hills
Estimated Cost
$171,887 ($34,377.00 City)
City Participation
$34,377.00
Delivery Method
City Forces / Public Bid – Grant-Funded Project (ADECA – RTP)
Greendale Road Sidewalk
Provide sidewalk connection from Crosshaven Drive to East Street while adding traffic calming elements to Greendale Road. Added as a priority sidewalk project due to the results of a traffic calming analysis that found that the observed speeds were outside of the standards desired according to the City’s Traffic Calming Policy for Residential Streets, as well as noted high pedestrian use. Click here to view the project drawings.
Activity / Status
Finalize public involvement of petition area; finalization of plans scheduled for spring 2026; estimated bid scheduled for fall 2026.
Location
Greendale Road
Managing Organization
City of Vestavia Hills
Start Date
Fall 2026
Estimated Cost
$958,754.89 ($191,750.98 City)
City Participation
$191,750.98
Delivery Method
Public Bid – Grant-Funded Project (ALDOT – TAP)
Highway 31 Gateway / Landscaping Project
Provide beautification to the southern gateway area, including signage, landscaping and drainage improvements:
- Stormwater/infrastructure improvements and repairs to properly direct the flow of stormwater to keep it from pooling on the roadway
- Improved median strip on U.S. 31 and on both sides of the highway
- Replacement of existing fencing behind the proposed wall structure
- Improvements to existing “southern temple” structure and grounds
- 15′ tall x 130′ long retaining wall to be installed parallel to Highway 31 North
- Additional (secondary) “Vestavia Hills” sign bearing the city’s name/logo on the opposite side of Highway 31 (near the existing Chevron station)
- Landscaping in the area; work to be performed in conjunction with ALDOT where warranted
The bid from Gillespie Construction was accepted at the October 13, 2025 meeting of the City Council. Click to view the bid documents. Click here to view additional gateway and infrastructure project information, including the civil plans for the project. Revised drawings were shared with the Council at their regular meeting on 12/08/2025. Click here to view the revised drawings.
Activity / Status
Finalize landscape on the north corner of Highway 31; finalize approval of letter change with ALDOT; approve contractor change order.
Location
Highway 31 at I-65
Managing Organization
City of Vestavia Hills
Start Date
January 2026
Estimated Cost
$1,222,872.70
Delivery Method
Public Bid – City-Controlled Project
Liberty Parkway at Urban Center Parkway – Traffic Signal
Improve safety of the Liberty Parkway & Urban Center Parkway intersection.
Activity / Status
Coordination with Jefferson County team to address questions and establish start date. Construction estimated to begin fall 2026.
Location
Liberty Parkway at Urban Center Parkway
Managing Organization
Jefferson County
Start Date
Fall 2026
City Participation
City to contribute $250,000
Delivery Method
Jefferson County Personnel – Joint/Partner Project (Jefferson County)
Massey Road
Road and sidewalk work is underway following a prolonged resolution of a water main relocation issue. Project includes sidewalk improvements, drainage improvements, new retaining wall, shoulder improvements, roadway widening and resurfacing.
Activity / Status
Wall construction to continue into early spring 2026; sidewalk installation and resurfacing to follow.
Location
Massey Road (Highway 31 to Columbiana Road)
Managing Organization
This is partially a federally funded project, administered by ALDOT; a 20% match of City funds has been used for the design and will be used for construction of the project.
End Date
Late summer 2026 (original completion date extended due to delay in water utility relocation)
Estimated Cost
$6,085,399.69 ($1,217,079.94 City)
City Participation
$1,217,079.94
Delivery Method
Public Bid – Grant-Funded Project (ALDOT – CMAQ)
Pedestrian Bridge
Provide connectivity from both west & east sides of Highway 31 in the vicinity of Wald Park and the Vestavia Hills Library in the Forest to provide a link to the existing sidewalk system that connects the City’s schools, libraries, parks and other features/amenities, and to improve the overall mobility and safety of pedestrians crossing Highway 31. Click to view design rendering #1 and design rendering #2, as well as the design information and location.
Activity / Status
Finalize vertical transportation tower and complete sidewalk work around tower base; estimated completion spring 2026.
Location
1251 Montgomery Highway
Managing Organization
This is partially a federally funded project, administered by ALDOT; a 20% match of City funds has been used for the design and construction of the project.
Start Date
August 2024
End Date
Late spring 2026
Estimated Cost
$5,306,663.43 ($1,060,714.45 City)
City Participation
$1,060,714.45
Delivery Method
Public Bid – Grant-Funded Project (ALDOT – CMAQ, DE, HPP & TAPBH)
Pedestrian Bridge – Continuation of Sidewalk
Provide connectivity from pedestrian bridge to existing sidewalk in front of Baumhower’s.
Activity / Status
Receive ALDOT approval for sidewalk extension; construction estimated to begin fall 2026.
Location
1251 Montgomery Highway
Managing Organization
City of Vestavia Hills
Start Date
Fall 2026
Estimated Cost
$93,100
Delivery Method
Selected Contractor – City-Controlled Project
Rocky Ridge Road at Dolly Ridge Road – Turn Lane
Reduce congestion at the Rocky Ridge Road and Dolly Ridge Road intersection by adding a right turn lane on Rocky Ridge northbound.
Activity / Status
Jefferson County finalizing right-of-way acquisition.
Location
Rocky Ridge Road at Dolly Ridge Road
Managing Organization
Jefferson County / City of Vestavia Hills Partnership
Start Date
Summer 2026
City Participation
Approximately $90,000 (City funded design; Jefferson County to fund construction)
Delivery Method
Jefferson County Personnel – Joint/Partner Project (Jefferson County)
Veterans Memorial Plaza
Provide Veterans Memorial Plaza.
Activity / Status
Finalize contract with low bid contractor and issue notice to proceed; estimated to commence work in spring 2026.
Location
Altadena Valley Park
Managing Organization
City of Vestavia Hills
Start Date
Spring 2026
Estimated Cost
$477,329.50
Delivery Method
Public Bid – City-Controlled Project
Drainage Projects
- Pipelining Projects
- Oakview Lane (final phase)
- Canyon Road & Pine Street
- Vesthaven Way (culvert replacement)
Pavement Management
First Step Pavement Management reviews the City’s streets on a three-year rotation, with the initial assessment being completed in 2022. Following their video assessment, each street is rated using the Pavement Condition Index (PCI). Streets are rated on a scale from 1 to 100, with 100 representing excellent condition and any score below 45 considered lost. Paving priorities are set based on PCI scores, site inspections and geographic distribution.
2026 Paving List (calendar year) & Resolution 5190: Rebuild Alabama Act
Current Locations – Work to Begin March 31, 2026
- Beaumont Drive
- Beaumont Circle
- Vesclub Drive
- Vesclub Circle
- Vesclub Lane
Estimated Cost
$477,329.50
Sidewalk Master Plan
The City of Vestavia Hills continues to install sidewalks to improve pedestrian connectivity and has developed a multi-year sidewalk master plan to guide future pedestrian projects to further connect the citizens of Vestavia Hills to the commercial areas and gathering spaces throughout the City.
Click to view the current Sidewalk Master Plan and Resolution 5122: Sidewalk Construction Policy.
Note that commercial districts along Highway 31, Rocky Ridge Road, Cahaba Heights Road, Crosshaven Drive and Green Valley Road have sidewalks shown on both sides of the road to provide additional walkable access to these areas. Future sidewalks shown in Liberty Park are based upon master plan information provided by Liberty Park Joint Venture. Future pedestrian elements to provide further connectivity are currently being studied and evaluated.
Private Projects Underway
- Ace Hardware – 680 Olde Towne Road
- Fifth Third Bank – 3010 Healthy Way
- Fifth Third Bank – 3178 Rush Street
- Liberty Park Day Spa – 1090 Lantern Way
- Liberty Park Eye Center – 3740 Corporate Woods Drive