City Projects

Road & Sidewalk Projects

Periodic delays should be anticipated in all project areas – please drive with caution. If you have any questions or concerns, contact City of Vestavia Hills Department of Public Services at 205.978.0150.
  • Cahaba Heights Road – Survey and preliminary layout of sidewalk project is complete. Design work is in progress. Click to view map of proposed sidewalk.
  • Cahaba River Road – Jefferson County is moving forward with widening along Cahaba River Road at Blue Lake/Healthy Way and Timberlake intersections. This will be completed as part of the roadway resurfacing project.
  • Cedardell Lane – Asphalt repairs are scheduled to begin July 24, 2019, near 1224 Cedardell Lane. The roadway will be open to local residents, but others should bypass the work area. Work will consist of removing the damaged sections of asphalt, leveling the subgrade and placing new asphalt. All work should be complete in approximately 2 weeks. Click here for project map.
  • Crosshaven Drive – Design work on this widening project is substantially complete. Utility coordination and right-of-way coordination/acquisition are currently underway. Bidding for this project is anticipated for fall 2019 and construction is anticipated to begin early 2020.
  • Dolly Ridge Road at Gresham Drive – Jefferson County is working to lengthen the northbound left turn lane on Dolly Ridge Road, as well as signal timing improvements, to better accommodate school traffic. Project completion is anticipated prior to August 8, 2019.
  • Dolly Ridge Road at Rocky Ridge Road – Jefferson County is working on traffic signal improvements at this intersection to better accommodate school traffic. Work includes installation of a dedicated left turn signal on Rocky Ridge Road. Installation of new poles to support signals is scheduled for Saturday, July 27. Project completion is anticipated prior to August 8, 2019.
  • East Street – Survey and preliminary layout of sidewalk project is complete. Design work is in progress. Click to view map of proposed sidewalk.
  • Gresham Drive – A drainage pipe replacement project under Gresham Drive is mostly complete. Work to stabilize the road should be complete within the next week. Click here for project map.
  • Liberty Parkway & South Liberty Road – The next phase of construction of a new roundabout is underway and will continue through August. This work will require a shift of travel lanes. Access to South Liberty Road will continue to be affected – right turns will be allowed, but left turns will need to follow the detour route. Drivers should proceed with caution and expect delays. Click here for project map.
  • Massey Road – This is an ALDOT-funded project – they control timeframe, awarding contract, etc. The City of Vestavia Hills is responsible for providing design services (through our consultant) and the design drawings to meet all ALDOT requirements. ALDOT comments are being addressed and revised plans will be submitted to ALDOT shortly. The City is working with utility companies to identify and resolve various conflicts. If there are no changes to the timeline, ALDOT will schedule construction to begin spring 2020. In the interim, pipe improvements are planned for July.
  • Mountain View Drive – Survey and preliminary layout of sidewalk project is complete. Design work is in progress. Click to view map of proposed sidewalk.
  • Overton Road at Liberty Parkway – Work consists of widening this section of Overton Road to accommodate a continuous 4-lane roadway from Liberty Parkway to the I-459 Access Road. Roadway construction is anticipated to be ongoing through summer 2019. (Additional work along Liberty Parkway near South Liberty Road is ongoing and includes construction of a new roundabout.) Click here for project map. For information regarding the road dedication, including a map of the dedicated roads and other FAQ’s, click Liberty Park road dedication.
  • Overton Road at Stoneleigh Drive – Drainage pipe replacement is scheduled to being July 26 and will require approximately two weeks to complete.
  • Pedestrian Bridge – The City of Vestavia Hills, in conjunction with the Alabama Department of Transportation (ALDOT), is in the preliminary design phase for the construction of a pedestrian bridge over Highway 31 (SR-3) in the City of Vestavia Hills at Wald Park and the Vestavia Hills Public Library. Design consultants presented information on the project during the April 8, 2019 City Council meeting and ALDOT approval is anticipated in the upcoming months. Click to view the conceptual design and location map.
  • Rocky Ridge Road/Dolly Ridge Road – Survey and preliminary layout of sidewalk project is complete. Design work is in progress. Click to view map of proposed sidewalk.
  • Shades Crest Road – To continue to serve you with the safest, most reliable energy available, Spire continues to upgrade pipelines along Shades Crest Road. This is a slow-moving project due to the amount of rock in the area, but work is progressing. The project is 60% percent complete and the goal is to complete the project by the end of September 2019. Crews will continue to work weekdays from 8:30am- 4pm, and some Saturdays starting at 9am. For safety and efficiency, lane closures in the immediate work area will be required during these hours. While work hours have been adjusted to minimize traffic congestion, this is a heavily travelled road and delays should be expected. Officers will be managing traffic during the lane closures to assure that traffic flows as smoothly as possible. This is a long-term project where work has been conducted in phases so that only one area of the roadway is affected at any given time. Paving of Shades Crest Road is anticipated beginning summer/early fall 2019. This is a Jefferson County through road and, as such, final scheduling is dependent upon the Jefferson County paving schedule. The City will continue to push for completion of the road paving immediately upon completion of the Spire project. In the interim, Jefferson County recently completed several pothole repairs. Spire project information & Spire project map
  • Sicard Hollow Road Pedestrian Tunnel – The City Council voted to accept the project bid for construction at their May 20, 2019 meeting. The Council also voted to approve a resolution authorizing construction engineering and inspection. At this time, construction is expected to commence mid- to late-summer.
  • Southwood Road/Granada Drive – A drainage pipe replacement project at this intersection is mostly complete. Final asphalt work is schedules to complete within the next two weeks.
  • 2018 Paving List & 2018 3-Year Paving Schedule – The 2018 Paving Schedule is a potential 3-year plan for paving poorly rated roads. Roads highlighted in red are potentially the first to be paved; then orange; then yellow. Roads highlighted in pink will be paved in conjunction with Spire upon completion of their gas pipeline improvement project.
  • Click to view the 2016 Sidewalk Master Plan

Emergency Road Closures

CLOSED: None. All Vestavia Hills roads are open.

Be sure to follow Vestavia Hills Police and Fire on social media for up-to-the-minute, accurate information:
VHFD – Facebook: @VestaviaHillsFire
VHPD – Facebook: @VestaviaHillsPolice; Twitter: @VHPD1032

Report emergencies by calling 911. Non-emergencies can be reported by calling VHPD at 205.823.1153. Downed trees, downed power lines or other hazardous road conditions can be reported via the Action Center app or by visiting https://bit.ly/VHActionCenter. Your report will be immediately routed to the appropriate first responder.

Report a power outage by calling Alabama Power at 800.888.2726.

Planning Projects

  • APPLE Intersection Project / Potential Study Intersections –
    (Click here for the map of Potential Study Intersections)
  • Dolly Ridge Road & Rocky Ridge Road (Jeff Co) – currently signalized; review signal operations and potential turn lane additions
  • Sicard Hollow Road & Blue Lake Drive (Jeff Co/Bham) – not currently signalized; review for safety, operational and sight line improvements
  • Shades Crest/Rocky Ridge Road/U.S. Highway 280 (Jeff Co/ALDOT) – currently signalized and coordinated with U.S. 280 system; capacity analysis
  • Highway 31 & Shades Crest Road (ALDOT/Jeff Co) – currently signalized; review signal operations and potential turn lane additions
  • Highway 31 & Columbiana Road (ALDOT/Jeff Co) – currently signalized; review signal operations and operational improvements
  • Highway 31/Old Creek Trail/Leona Way (ALDOT) – currently signalized; review signal operations, operational improvements with access management
  • Columbiana Road & Shades Crest/Vestaview (Jeff Co) – currently signalized; pedestrian access
  • Highway 31/City Hall/Sprouts (ALDOT/Jeff Co) – currently signalized; pedestrian access
  • Highway 31/Pizitz Drive (ALDOT/Jeff Co) – currently signalized; pedestrian access
  • River Run Drive & River Run Trail (Jeff Co/Bham) – not signalized; analysis for need to add 3‐way stop or other means of traffic control
  • Jacobs Road & Massey Road (City of Vestavia Hills) – not signalized; review safety and sight line improvements, right‐of‐way constraints
  • Acton Road APPLE Grant (Feasibility Study) – in design phase
  • Wald Park Master Plan – awaiting Community Spaces Plan approval by Council
  • Crosshaven APPLE grant – for more information, visit Crosshaven Drive Corridor Study
  • East Street Analysis and Planning – for more information, visit East Street Data Collection Summary

Infrastructure & Community Spaces Plan

A Comprehensive Plan

The Infrastructure & Community Spaces Plan is a comprehensive proposal for improvements to a broad range of activities throughout the City of Vestavia Hills. This plan was initially based on the strategic drivers established in the 2015 Recreation and Athletics Master Plan:

  • Reposition quality of life assets to reflect the Vestavia Hills brand and effectively recruit and retain families
  • Elevate the quality of existing facilities to comprehensively serve the recreational interests of all members of the community regardless of age
  • Increase the capacity of City athletic facilities to ensure that Vestavia Hills youth sports programs deliver a high impact and consistent experience that result in the athletic and personal development of all participants

The plan has since been expanded to include not only recreational facilities, but also community infrastructure improvements.

Plan Components

During a series of public meetings, stakeholders were encouraged to complete surveys for each of the proposed Infrastructure & Community Spaces Plan components. Upon completion of stakeholder meetings, along with input from various City staff and boards, TCU presented their suggestions during the January 18-19, 2018 Council work session. Specifics for each area of improvement can be accessed at TCU Community Spaces Plan. Citizens and stakeholders are encouraged to comment on the plan components by clicking on “Community Spaces Plan questions and comments” at https://vhal.org/vestavia-hills-listens/. Following is a summary of the major plan components and the estimated cost for each:

  • Road Capacity & Sidewalk Improvement Project: $4,611,000
  • Sidewalk Installation: $2,500,000
  • Road Paving: $2,200,000
  • Stormwater Infrastructure Improvements: $550,000
  • Refinance Gold’s Gym Property: $8,900,000
  • Community Spaces Plan Implementation: $38,598,971
    • Wald Park $15,429,766
    • Cahaba Heights $7,398,815
    • Community Building $15,270,390
    • New Merkel House $500,000

TOTAL ESTIMATED COST: $57,359,971

Project Dates

  • Wald Park:
    • Bid Opening: Tuesday, July 2, 2019 at 4 p.m.
    • Anticipated Notice to Proceed: August 1, 2019
    • Substantial Completion Dates:
    • Waldridge Road Turn Lane: October 1, 2019
    • Baseball Complex: March 1, 2020 (including dedicated parking and entry points)
    • Pool Facility: May 25, 2020 (including dedicated parking and entry points)
    • Remainder of the work at Wald Park: 455 days following the official Notice to Proceed
    • These schedules, as well as traffic flow during the construction period, has been communicated with BOE leadership.
  • Community Building:
    • Bid Opening: Tuesday, August 18, 2019
    • Anticipated Notice to Proceed: September 10, 2019
    • Construction Duration: 425 days following the official Notice to Proceed
  • Cahaba Heights:
    • Official Notice to Proceed: July 1, 2019
    • Substantial Completion: 365 calendar days
  • New Merkel House:
    • Bid Opening: September 2019
    • Substantial Completion: Summer 2020
  • Crosshaven Drive:
    • Utility work will not be able to commence until all acquisitions are complete, by both the County and the City.
    • Acquisition critical path belongs to Probate Court of Jefferson County.
    • Utility work includes the relocation of power and water along the entire corridor.
    • Utility work will take no longer than 6 weeks.
    • Once Probate rules on acquisitions and utility work can be scheduled, advertising and the bidding process will begin immediately. Advertising will run for 3 weeks in 3 newspapers.
    • Following the advertising period, contractors will be prequalified, attend a mandatory pre-bid meeting and then submit bid.
    • Once utilities are relocated, the contractor will be ready to mobilize immediately.
    • Construction Duration: 255 days
    • Anticipated Notice to Proceed: January 15, 2020
  • SHAC AML Grant Project:
    • Bid Opening: July 2019
    • Anticipated Notice to Proceed: August 13, 2019
    • Construction Duration: 185 days

Activity Updates

  • July 19, 2019: The Wald Park bid tabulation was discussed at the Council work session. Bid approval will be on the agenda for the Monday, July 22 Council meeting with a request for unanimous approval. If approved, the next phase of work at Wald Park will begin July 25, 2019. Click HERE to view the bid tab. 
  • June 25, 2019: City Manager Jeff Downes hosted a Lunch & Learn where he presented an update on the construction plans for Cahaba Heights Athletic Complex, Wald Park and the Community Building. Click HERE to view the presentation. Click HERE to view the presentation notes (provided by Councilor Kimberly Cook).
  • June 24, 2019: Updated project dates were presented during the City Council meeting. (See above)
  • June 10, 2019: Construction documents for the Wald Park and Community Building projects were presented during the City Council Work Session by representatives from TCU. Click HERE to view the full presentation. At the Council meeting, the bid for renovation/construction of the Cahaba Heights athletic complex was unanimously approved. The low bidder is Stone Building LLC and their bid is within the constraints of previously established budget for this project. The bid documents are available for viewing in the June 10, 2019 Council Agenda Packet at https://vhal.org/government/agendas/.
  • March 12, 2019: City Manager Jeff Downes presented an update on the Infrastructure & Community Spaces Plan at the Vestavia Hills Chamber of Commerce luncheon. Click HERE to view the presentation.
  • February 4, 2019: The Wald Park, Cahaba Heights Athletic Fields and Community Building projects have moved into the Design Development stage. Design drawings/renderings for these projects were presented during the City Council Work Session by representatives from Williams Blackstock Architects. Click HERE to view the full presentation.
  • October 15, 2018: Design considerations for the Cahaba Heights Athletic Fields and the Community Building were presented and discussed during the City Council work session.
  • September 24, 2018: Ordinance Number 2801 – an Ordinance accepting a bid for the Wald Park Initial Site Package – was approved by unanimous vote of the City Council. Site work at Wald Park will commence this week.
  • September 17, 2018: Design considerations for Wald Park were presented and discussed during the City Council work session.
  • August 20, 2018: TCU CSP Projects Report – July 2018 presented during City Council work session
  • May 14, 2018: The corporate office of Gold’s Gym initiated conversations to reach an agreement for the early termination of the lease contract on property located at 1090 Montgomery Highway, effective June 30, 2018, with a termination payment to the City of Vestavia Hills in the amount of $510,000. The Mayor and City Council approved Resolution 5051, authorizing the City Manager to execute and deliver this full and final settlement agreement, release and lease termination for the Gold’s Gym property. As a part of the Community Spaces Plan, Gold’s Gym will become the new Community Building and will have nearly 90,000-sf of space for people of all ages to utilize for senior programming, arts & crafts, dances, basketball games, etc. This Community Building is just a small part of the overall plan to renovate and replace aging infrastructure and facilities city-wide.
  • April 16, 2018: The City of Vestavia Hills has been awarded a grant from ALDOT (TAP 2018) for $280,000. The grant’s purpose is to construct a sidewalk/trail connection from Gold’s Gym to Wald Park. For additional details of the grant application, along with Governor Ivey’s award letter, visit TAP Grant – Sidewalk Connector. This grant furthers efforts to fully integrate City facilities along Highway 31.
  • April 9, 2018: The City Council voted to approve 1% sales tax and 3% lodging tax increases. To access meeting minutes or to view the archived meeting video, visit Current Agendas & Agenda Packet.
  • April 3, 2018: Town Hall Meeting Presentation
  • January 18, 2018: TCU CSP Plan
  • June 12, 2017: City Council approved Resolution 4951 authorizing the Mayor and City Manager to execute and deliver a contract for the implementation stage of the Community Spaces Plan for a program manager (TCU).

Archived Files