> Drainage Assessments
> Ongoing & Future Drainage Projects
> Recently Completed Drainage Projects
> Planning Studies
Drainage Assessments
- Upper Highway 31/Shades Crest/Vestavia Lake Drainage Assessment – Residential Informational Meetings led by Schoel Engineering team have concluded. Click the link below to view the community presentations.
November 29: https://vimeo.com/778210848
November 30: https://vimeo.com/778211169
December 5: https://vimeo.com/778211380
December 8: https://vimeo.com/779660165Consultant: Schoel Engineering
Updated: 12/12/2022
- Dolly Ridge Drainage Assessment – More information to come.
- Fairhaven Drive Drainage Assessment – More information to come.
- Blind Brook Lane
Scope of Work (based on conceptual in-house review): Install approx. 60 LF of 22” x 13” RCP and two new inletsConsultant: In-houseProject Status Update: Next step should project move forward would be engaging a Consultant to complete survey and design services to determine feasibility and costs
- Ridgedale Drive
Scope of Work (public): (1) Install approx. 880 LF of new 18” pipe; (2) Install 4 new curb inlets; (3) Install approx. 1,100 LF of new 30” valley gutterConsultant: Sain Associates
- Ridgely Drive
Scope of Work: Planning study to review existing conditions and develop improvement recommendations to address deficiencies (will likely involve public and private improvements)Consultant: Sain Associates
- Tyler Road at Twin Branch
Scope of Work: Survey and design services to assist with replacement of storm pipe failure at intersectionConsultant: TTLProject Status Update: TTL is is conducting the study/survey phase. 2/10/2023
Ongoing & Future Drainage Projects
- Autumn Lane
Scope of Work (public): Install new 48” pipe under Autumn LaneConsultant: Sain AssociatesProject Status Update: Project has been put on hold due to private property upgrades required in order for project to be successful.
- Buckhead Road
Scope of Work: (1) Install 2 new inlets and 18” pipe under road; (2) Grade in grass swale and install rip rapConsultant: In-houseProject Status Update: Scheduled early March.
- Dolly Ridge Road
Scope of Work (public): (1) Install 37 LF 28” x 18” RCP; (2) Install new Type-S single wing inlet; (3) Install 2 new junction boxesConsultant: Caprine EngineeringProject Status Update: Construction drawings have been completed. Public Works has pipe available. Work ready to be scheduled.
- Fairhaven/Midland/Poe
Scope of Work: (1) Replace concrete headwall and construct a new concrete flume; (2) Replace existing 60” corrugated metal pipeConsultant: Engineering Design Group, LLCProject Status Update: These are initial 2 improvements recommended as part of stormwater masterplan study for the area. Study is ongoing. Work ready to be scheduled.
- Oakview Lane
Scope of Work (Phase III): Replace old metal pipe that has collapsed along Oakview Lane and perform associated inlet box and roadway repairsConsultant: Caprine EngineeringContractor: Tomahawk ConstructionProject Status Update: 12/1/2022 Phase 3 complete. Phase IV – future
- Southwood Road (1930)
Scope of Work: (1) Replace approx. 62 LF of existing 18” RCP in right-of-way; (2) Install headwall and rip rap at outfallConsultant: Sain AssociatesProject Status Update: Next steps are to coordinate with property owners and schedule work
- Southwood Road (1957)
Scope of Work: (1) Replace approx. 34 LF of existing 24” pipe under roadway; (2) Install new inlets, approx. 26 LF of new 24” pipe & headwall w/ rip rap; (3) Replace approx. 130 LF of valley gutterConsultant: Sain AssociatesProject Status Update: Public Works has pipe available. Work ready to be scheduled.
Recently Completed Drainage Projects
Maintenance Area 1 | Maintenance Area 4 | ||
Balfour Drive | Blue Lake Drive at Elmore | ||
Graylynn Drive | Cahaba Heights Ball Fields | ||
Hickory Road | Crosshaven Drive | ||
Mission Road | Lewis Street | ||
Tyler Place | Noel Drive at Valley Park Drive | ||
Vestavia Place | Noel Drive at Valley Park Place | ||
2 pipes on Massey Road | Oakview Lane Phases 2 & 3 | ||
Maintenance Area 2 | Old Looney Mill Road | ||
Biltmore Avenue | Overton Road | ||
Blueberry Lane | Overton Road at Stoneleigh | ||
Morgan Drive | Ridgely Drive | ||
Pizitz Drive | Ridgely Drive at North Cahaba | ||
Southwood Road | Sheffield Drive | ||
Trousdale Street | Stoneleigh Drive | ||
Valley Park Drive | |||
Maintenance Area 3 | White Oak Drive at Valley Park Place | ||
Beaumont at Monterey | Kyle Lane | ||
Beaumont at Shades Crest | Blue Lake Drive Pipe Replacement | ||
Gresham Drive | |||
Leslie Ann Road | |||
Milbrook Road | |||
Skyland Drive | |||
Comer Circle |
Planning Studies
- Traffic Operations APPLE Study (Phase 1) – This study was initiated by the City through the Advanced Planning, Programming and Logical Engineering (APPLE) program developed by the Regional Planning Commission of Greater Birmingham (RPCGB) and includes evaluation of traffic operations at the following intersections:
- Rocky Ridge Road at Dolly Ridge Road
- Sicard Hollow Road at Blue Lake Drive/Cahaba Heights Road (proposed roundabout) Sain Associates Engineering presentation to the Council 05.23.2022
- Rocky Ridge Road at Highway 280
- Highway 31 at Shades Crest Road
- Highway 31 at Columbiana Road/I-65 Northbound Ramps
- Highway 31 at Vestavia Plaza/City Hall
- Highway 31 at Pizitz Drive/Vestavia Forest Place
- Columbiana Road at Shades Crest Road/Vestaview Lane
- Dolly Ridge Road at Gresham Drive
- APPLE Potential Intersection Study:
- Dolly Ridge Road & Rocky Ridge Road (Jeff Co) – currently signalized; review signal operations and potential turn lane additions
- Sicard Hollow Road & Blue Lake Drive (Jeff Co/Bham) – not currently signalized; review for safety, operational and sight line improvements
- Shades Crest/Rocky Ridge Road/U.S. Highway 280 (Jeff Co/ALDOT) – currently signalized and coordinated with U.S. 280 system; capacity analysis
- Highway 31 & Shades Crest Road (ALDOT/Jeff Co) – currently signalized; review signal operations and potential turn lane additions
- Highway 31 & Columbiana Road (ALDOT/Jeff Co) – currently signalized; review signal operations and operational improvements
- Highway 31/Old Creek Trail/Leona Way (ALDOT) – currently signalized; review signal operations, operational improvements with access management
- Columbiana Road & Shades Crest/Vestaview (Jeff Co) – currently signalized; pedestrian access
- Highway 31/City Hall/Sprouts (ALDOT/Jeff Co) – currently signalized; pedestrian access
- Highway 31/Pizitz Drive (ALDOT/Jeff Co) – currently signalized; pedestrian access
- River Run Drive & River Run Trail (Jeff Co/Bham) – not signalized; analysis for need to add 3‐way stop or other means of traffic control
- Jacobs Road & Massey Road (City of Vestavia Hills) – not signalized; review safety and sight line improvements, right‐of‐way constraints
- Acton Road APPLE Grant (Feasibility Study) – in design phase
- Wald Park Master Plan – awaiting Community Spaces Plan approval by Council
- Crosshaven APPLE grant – for more information, visit Crosshaven Drive Corridor Study
- East Street Analysis and Planning – for more information, visit East Street Data Collection Summary